Greg and Shahab,
Thank you for taking the time earlier today to help us work
through some of the issues for the subject plan and the related plat. Here
is a summary of our findings and follow-ups:
·
High Mesa Consulting Group (HMCG) will revise the
note on the plat to identify the remaining blanket drainage easement as being
the responsibility of the Owner of Tract B, as opposed to former Lot
2.
·
Our Building Permit Plans will include a berm and
sediment/nuisance flow trap to prevent cross-lot drainage from Tract A to Tract
B, thereby eliminating the need for an easement.
·
HMCG will provide you with supplemental
calculations to support the pipe sizing and the feasibility of collecting flows
in a cul-de-sac.
·
HMCG will take a closer look at the overflow
condition and provide curb cuts downstream of the turn lane to allow any street
flow to enter the ditch.
·
HMCG will propose to the Design Team that the
sidewalk along Central be asphalt pavement seeing how it will likely be removed
in the near future with storm drain construction.
As a follow-up, we present the following
information:
·
Review of the existing intersection reveals that
the high point is set at 100.64, slightly higher than the overflow point on the
top of the sidewalk culvert (see attached excerpt from topo). As such, the
initial overflow after the 18” pipe and sidewalk culvert capacity is indeed to
the ditch. Further review of our topo and from Google Earth confirms that
there is actually a downstream curb cut before the intersection at Unser.
Based on these findings, it does not appear that the overflow to street flow
issue is as significant as we thought earlier, but still does exist. I
will show this to the Design Team tomorrow and recommend that a curb opening and
rundown be added to the building permit plans.
·
Attached herewith are supplemental calculations
that show the open channel gravity flow of 97 cfs (291/3) at a depth of 3.6 ft
in a 48” pipe. Also attached are pressure calculations that start with an
additional 1.85 ft of head above the 3.6 ft normal depth to simulate the head
loss for a 90 degree bend which is conservative compared to a 90 degree manhole
turn. The pressure calculations show that the required head at the cattle
guard results in a hydraulic grade line right at the flowline or grate elevation
in the cul-de-sac (no popping manhole lids or backing up).
·
I have seen many ways to look at inlet
capacities. In this case, we will have some flow velocity, but effectively
a sump due to the curb at the cul-de-sac. Assuming the grates are a
submerged orifice, it would take 16.2 standard city grates to accept 291
cfs. The cul-de-sac at the point beyond the car wash entrance is about 50
ft wide, allowing 15 grates. If you add the existing single “C”, and the
proposed double “C” we propose to add at the low spot in the entrance (where the
sidewalk culver is), you get 18 grates, total. This would result in no
street flow.
Based on the above, I believe your questions and comments can
be addressed for infrastructure list approval (3-48” pipes can carry the flow
and a cattle-guard type of structure could intercept the flow). If you
concur, please let me know and copy Stephen Woodall who has requested an
“endorsement” of the infrastructure list from Hydrology before he approved our
estimate.
Thanks again,
Let me know if you have any questions.
Graeme